Chapel Wharf construction project by PCE

Chapel Wharf updates

PCE Ltd are in residence at Dandara’s Chapel Wharf project in Manchester. The 4.2 acre site adjacent to the Lowry Hotel and between the River Irwell and Chapel Street in Salford, Manchester is currently being built by Main Contractor Sir Robert McAlpine.

  • PCE at the top of the construction site safety board at Chapel Wharf

Health & Safety success at Chapel Wharf

May 16th, 2019|Comments Off on Health & Safety success at Chapel Wharf

Continuous focus on construction site safety PCE has an exemplary reputation for all aspects of Health & Safety in the construction industry as a major provider of Offsite engineered HybriDfMA structural solutions. This has [...]

  • A high quality of construction with a fast onsite construction period of only 90 weeks
  • Precast concrete cross wall construction techniques with precast architectural sandwich panels and balcony units
  • A fast onsite construction period of only 90 weeks and maintaining exemplary standards of Health and Safety
  • PCE's HybriDfMA Living Systems approach enabled construction without any external scaffolding
  • As the towers progressed fit out could commence just 3 floors below
  • This project clearly demonstrates PCE's HybriDfMA Living Systems approach
  • PCE Ltd has worked closely with Main Contractor Sir Robert McAlpine from the start of the tender
  • The last offsite engineered structural precast unit has been successfully erected by PCE

Update 18 – Chapel Wharf topped out!

May 2nd, 2019|Comments Off on Update 18 – Chapel Wharf topped out!

Digital expertise combined with offsite construction The last offsite engineered structural precast unit has been successfully erected on the twenty three storey high tower block, one block of four that comprise the Dandara high rise [...]

  • PCE receive SHEQ Award at Chapel Wharf project

Chapel Wharf update 17 – PCE’s SHEQ commitments recognised

March 21st, 2019|Comments Off on Chapel Wharf update 17 – PCE’s SHEQ commitments recognised

Safety Health Environment and Quality award in Manchester Construction of Developer Dandara's 995 build to rent apartment scheme at Chapel Wharf is nearing completion, with PCE Ltd’s constant commitment to site safety once again being to [...]

  • PCEs Chapel Wharf development in Manchester
  • Blocks C and D on PCEs Chapel Wharf project
  • A Design and Build Offsite engineered solution adopted by PCE
  • High standards of construction are being achieved by PCE in Manchester
  • The Chapel Wharf Salford residential project for developer Dandara
  • External architectural precast concrete cladding panels

Chapel Wharf update 16 – installing level 18 walls on block D

January 30th, 2019|Comments Off on Chapel Wharf update 16 – installing level 18 walls on block D

...and floor units on level 14 of block C Work is continuing rapidly on the two remaining blocks of PCE Ltd's Chapel Wharf project in Salford, Manchester. With work having been completed on blocks A [...]

  • The remaining two towers at Chapel Wharf are Blocks and D
  • Offsite pre-glazed external architectural envelope and balconies

Chapel Wharf update 15 – progress on blocks C and D and latest safety award

December 18th, 2018|Comments Off on Chapel Wharf update 15 – progress on blocks C and D and latest safety award

Offsite pre-glazed external architectural envelope PCE Ltd's work is proceeding at a good pace on blocks C and D of the nine hundred and ninety five unit Build to Rent apartment scheme being built by Sir [...]

  • 995 Build to Rent apartment scheme being built by Sir Robert McAlpine
  • PCEs Offsite Engineered predominately precast concrete crosswall structural approach
  • All the blocks are being constructed full height including the Offsite pre-glazed external architectural envelope
  • PCE's pre-glazed external architectural envelope in Manchester

Chapel Wharf update 14 – first two towers structurally topped out

October 17th, 2018|Comments Off on Chapel Wharf update 14 – first two towers structurally topped out

The precast concrete crosswall structural approach The first two apartment blocks have been structurally completed within the agreed construction programme as a result of PCE’s Offsite Engineered predominately precast concrete crosswall structural approach used on [...]

  • PCE Ltd are building at Dandara's Chapel Wharf project in Manchester
  • PCEs method of Offsite manufacture requires a reduced on-site workforce
  • PCEs collaborative approach will result in the four precast concrete structures

Chapel Wharf update 13 – the top 5 offsite construction advantages

August 29th, 2018|Comments Off on Chapel Wharf update 13 – the top 5 offsite construction advantages

Crosswall construction with precast concrete Construction work by PCE Ltd is progressing at an impressive pace on the site of developer Dandara's nine hundred and ninety five build-to-rent apartment scheme at Chapel Wharf in Salford. [...]

  • On site construction progress of the Chapel Wharf Salford, Manchester
  • PCE Ltd is the specialist Design and Build Contractor
  • Block D external sandwich unit being erected
  • Block C erecting external sandwich units to level 5
  • Blocks A and B will be complete in 2 more levels
  • External architectural precast concrete cladding panels

Chapel Wharf update 12 – external sandwich panels and pre-stressed floor units

August 22nd, 2018|Comments Off on Chapel Wharf update 12 – external sandwich panels and pre-stressed floor units

Lower roof levels on two blocks now complete PCE Ltd has been employed as the specialist design and build contractor for the four tower blocks of the Chapel Wharf residential project, which is located in [...]

  • Precast concrete offsite engineered component at Chapel Wharf in Manchester
  • PCE Ltd is the specialist design and build contractor for the four tower blocks
  • PCE is constructing level 12 at Block A in Manchester
  • After 37 weeks on site PCE had erected over 3400 units
  • The high standards of construction being achieved by PCE are evident
  • Offsite construction methods at Chapel Wharf in Salford

Chapel Wharf update 11 – 3,400 offsite engineered precast units in 37 weeks

June 18th, 2018|Comments Off on Chapel Wharf update 11 – 3,400 offsite engineered precast units in 37 weeks

33% of the precast concrete units installed for residential construction project PCE’s offsite Hybrid engineered approach to construction (HybriDfma) requires a reduced on-site workforce, provides enhanced Health and Safety, and ensures speed of construction and a [...]

  • Precast unit concrete 10.21m in length
  • A 21 tonne precast concrete units being craned into position
  • On site construction progress of the Chapel Wharf Manchester residential project
  • PCE Ltd specialist Design and Build Contractor appointed by Sir Robert McAlpine
  • PCE installing offsite engineered precast concrete units

Chapel Wharf update 10 – a 21 tonne 10.21m wide precast unit arrives on site

June 5th, 2018|Comments Off on Chapel Wharf update 10 – a 21 tonne 10.21m wide precast unit arrives on site

Delivered on a "just in time" basis Clear blue skies over Manchester witnessed the installation of the heaviest internal precast concrete wall unit to date at Dandara’s Chapel Wharf project in Manchester.  PCE Ltd are [...]

  • A total of only 38 PCE employees are required on site
  • The highly trained staff include 2 Graduate Engineers from Nottingham Trent University

Chapel Wharf update 9 – how all this can be achieved with only 38 on site staff

May 31st, 2018|Comments Off on Chapel Wharf update 9 – how all this can be achieved with only 38 on site staff

The benefits of leaving behind the "traditional" construction approach A total of only thirty eight employees from PCE Ltd, comprising of highly skilled site operatives and technical and site management, are located on site currently [...]

  • After 34 weeks on site PCE had erected over 2,900 units
  • High standards of construction being achieved by PCE
  • On site construction progress of Chapel Wharf Salford
  • Four tower blocks up to 23 storeys tall being built by PCE

Chapel Wharf update 8 – 2,900 offsite precast units in 34 weeks

May 30th, 2018|Comments Off on Chapel Wharf update 8 – 2,900 offsite precast units in 34 weeks

How offsite manufacture keeps onsite construction moving The on site construction of Chapel Wharf, a residential project in Salford, Manchester for developer Dandara, is making considerable and rapid progress. PCE Ltd has been engaged as the specialist [...]

  • PCEs Chapel Wharf Team that has won the monthly Health & Safety Award

Chapel Wharf update 7 – PCE team scoops monthly safety award

May 23rd, 2018|Comments Off on Chapel Wharf update 7 – PCE team scoops monthly safety award

Top of the safety league at Manchester construction project PCE Ltd's Team has won the monthly Chapel Wharf  project Health & Safety Award for April 2018 - being the top of the league table with 61 [...]

  • PCEs method of Offsite manufacture requires a reduced on site workforce
  • PCE Ltd in residence at Dandaras Chapel Wharf project in Manchester
  • Offsite construction produces the benefit of a reduction in the schemes carbon footprint
  • PCE Ltd worked with Sir Robert McAlpine during the tender period to develop an Offsite design and build solution
  • Offsite manufacture ensures speed of construction and a high quality build
  • Each block will be built in crosswall construction with precast concrete being used

Chapel Wharf update 6 – offsite design and build

February 27th, 2018|Comments Off on Chapel Wharf update 6 – offsite design and build

Collaborative approach with Sir Robert McAlpine PCE Ltd's collaborative approach with Main Contractor Sir Robert McAlpine will result in the four precast concrete structures, costing approximately £24 million, being erected on site over a 22 month programme. Dandara's [...]

  • PCEs method of Offsite manufacture requires a reduced on-site workforce
  • The scheme has been designed by Architect Axis Mason and WSP are the client’s consulting engineers
  • PCEs method of Offsite manufacture requires a reduced on-site workforce
  • Developer Dandara's 995 Build to Rent apartment scheme at Chapel Wharf

Chapel Wharf update 5 – crosswall construction with precast concrete

February 13th, 2018|Comments Off on Chapel Wharf update 5 – crosswall construction with precast concrete

Offsite manufacturing benefits evident in Manchester PCE Ltd's work is continuing apace at Dandara's build to rent apartment scheme at Chapel Wharf in Salford, Manchester, where the benefits of offsite manufacture are becoming evermore apparent. The [...]

  • PCE constructing four precast concrete structures
  • PCEs Offsite design and build solution for the four high rise apartment blocks
  • Developer Dandara's 995 Build to Rent apartment scheme at Chapel Wharf
  • The scheme has been designed by Architect Axis Mason and WSP are the clients consulting engineers
  • Precast concrete is being used for the crosswalls, cores, balconies, solid floor slabs, stairs and landings

Chapel Wharf update 4 – level 7 construction underway

January 22nd, 2018|Comments Off on Chapel Wharf update 4 – level 7 construction underway

New levels on blocks A and B PCE Ltd are now underway with the construction of level 7 of Block A and level 6 of Block B at Dandara's build to rent apartment scheme at Chapel [...]

  • Offsite construction improves project quality
  • Offsite construction improves project quality
  • PCEs offsite manufacturing benefits
  • Greater speed of construction with offsite methods
  • Offsite construction by PCE results in reduced onsite workforce
  • Improved Health and Safety results from offsite construction

Chapel Wharf update 3 – offsite precast manufacturing benefits

November 6th, 2017|Comments Off on Chapel Wharf update 3 – offsite precast manufacturing benefits

Significant carbon footprint reduction resulting Developer Dandara's 995 build to rent apartment scheme at Chapel Wharf, a 4.2 acre site adjacent to the Lowry Hotel and between the River Irwell and Chapel Street in Salford, [...]

  • Precast concrete construction in Manchester
  • Crosswall construction for Manchester project by PCE Ltd
  • The Chapel Wharf development will consist of four high rise apartment blocks
  • Precast concrete unit being lowered into position
  • Offsite focussed development will feature precast structures by PCE Ltd

Chapel Wharf update 2 – precast concrete panels arrive onsite

September 12th, 2017|Comments Off on Chapel Wharf update 2 – precast concrete panels arrive onsite

Crosswall construction for Manchester project The Chapel Wharf development will consist of four high rise apartment blocks that comprise the development, ranging from 13 to 23 storeys in height. The scheme has been designed by Architect [...]

  • Build to Rent apartment scheme at Chapel Wharf
  • PCE are to begin work at Chapel Wharf in Manchester
  • PCE will be erecting 4 precast concrete structures
  • PCEs 22 month construction programme begins in Manchester

Chapel Wharf project underway in Manchester

September 11th, 2017|Comments Off on Chapel Wharf project underway in Manchester

Offsite focussed development will feature precast structures Developer Dandara's 995 Build to Rent apartment scheme at Chapel Wharf, a 4.2 acre site adjacent to the Lowry Hotel and between the River Irwell and Chapel Street [...]