HybriDfMA assembly approach removed the need for use of tower cranes and potential oversailing problems with close neighbouring properties, reducing risk, programme, and cost.
1,805 HybriDfMA components assembled to construct onsite the 101 dwelling apartment block in just 27 weeks by only ten multi-disciplinary site operatives.
HybriDfMA assembly approach removed the need for use of tower cranes and potential oversailing problems with close neighbouring properties, reducing risk, programme, and cost.
Safety considerations highly prioritised at digital design stage and carefully followed through project manufacturing and assembly stages.
PCE’s Quality Standards implemented through design, manufacture and on-site assembly ensured accurate and rapid build process.
1,805 HybriDfMA components assembled to construct onsite the 101 dwelling apartment block in just 27 weeks by only ten multi-disciplinary site operatives.
The HybriDfMA assembly approach removed the need for use of tower cranes and potential oversailing problems with close neighbouring properties, reducing risk, programme, and cost.