Project Description

Lower Broughton residential development, Salford

Safety

All phases of the 6 podium and 2 car park structures assembled accident free.

Quality

PCE’s Extensive Quality Assurance procedures ensured all precast concrete components were manufactured offsite to within exacting quality standards.

Speed

1,829 Precast Concrete Components used to form the 2 carparks and 6 residential podiums, installed in 24-construction weeks, including all insitu structural topping.

Value

Phased delivery of the 8 structures used in a flood plane area to raise accommodation and parking above any potential flood levels.

Location: Salford, UK
Clients: Salford City Council and Countryside Properties.


The benefits of HybriDfMA Frames System construction:

1,829 Precast Concrete Components used to form the 2 carparks and 6 residential podiums, installed in 24-construction weeks, including all insitu structural topping.


Phased delivery of the 8 structures used in a flood plane area to raise accommodation and parking above any potential flood levels.