14,000 offsite engineered components in 40 week programme

HMP Fosse Way construction works underway

PCE Ltd has commenced construction of the HybriDfMA Secure – Prison System at the major redevelopment project, HMP Fosse Way.

 

Working in collaboration with Main Contractor Lendlease, PCE will deliver the Secure Accommodation Houseblocks, Care and Separation Unit and Entrance Building. The first Houseblock along with the Entrance Building have commenced, with the first precast elements arriving on site and being installed.

 

This marks commencement of a 40-week construction programme which will see PCE deliver nine buildings comprising around 14,000 precast components.

Let's Talk