University of Leeds, Sir William Henry Bragg Building updates

A new £96m development, the Sir William Henry Bragg Building, will be constructed to create an integrated campus for Engineering and Physical Sciences at the University of Leeds for Leeds University Campus Developments, to build on a shared interaction between these disciplines. 

  • Hot rolled and Delta Beam steel sections, insitu concrete and precast concrete components
  • PCE on site at The Sir William Henry Bragg Building in Leeds
  • Construction of the ground floor structure is well underway at Leeds University laboratory projectat Leeds University laboratory project
  • PCE's Delta Beam steel sections, insitu concrete and precast concrete components

Leeds University update 3 – the Offsite engineered Hybrid structure approach

May 15th, 2019|Comments Off on Leeds University update 3 – the Offsite engineered Hybrid structure approach

Sir William Henry Bragg Building PCE Ltd's multi-skilled workforce is making good progress with construction of their HybriDfMA structural frame system for The Sir William Henry Bragg Building, a Leeds University laboratory project, overcoming the [...]

  • PCE on site at the fortcoming state of the art teaching and research facility
  • PCE's precast concrete components for the basement and ground floor construction
  • Construction of University of Leeds Sir William Henry Bragg Building
  • PCE’s HybriDfMA frame solution has started on site in Leeds
  • Below ground superstructure works completed in just 12 weeks
  • The composite precast and insitu concrete wall will form the watertight inner lining of the basement box

Leeds University update 2 – below ground elements require only 12 weeks and 10 people

March 25th, 2019|Comments Off on Leeds University update 2 – below ground elements require only 12 weeks and 10 people

The HybriDfMA advantage PCE’s HybriDfMA frame solution has started on site within the basement at BAM Construction's ICEPS Integrated Campus for Engineering and Physical Sciences project for the University of Leeds. The composite precast and insitu [...]

  • The well proven HybriDfma approach will be used on the Sir William Henry Bragg Building

New project update – University of Leeds, Sir William Henry Bragg Building

October 22nd, 2018|Comments Off on New project update – University of Leeds, Sir William Henry Bragg Building

Sir William Henry Bragg Building, University of Leeds A new £96m development, the Sir William Henry Bragg Building, will be constructed to create an integrated campus for Engineering and Physical Sciences at the University of [...]