Past Projects

Precast tunnel watercourse diversion

On time despite weather challenges.

The structure was part of a major multi-million pound scheme to dual the Heads of the Valleys road in South Wales.

The new 230-metre long tunnel forms part of a reservoir watercourse diversion, situated some 30 metres below the widened A465 road from Brynmawr to Tredegar.

The contract on behalf of Carillion to erect the tunnel using Reinforced Earth’s TechSpan® precast concrete segments, was completed to programme despite some challenging conditions in the recent “rainy season”.

In all, PCE installed some 147 arch units weighing up to 20 tonnes each to form the tunnel and a further 18 scalloped units which were placed at the entry and exit to the structure.

Following completion of the first tunnel, Carillion then awarded PCE work on a smaller tunnel nearby using the Bebo arch system, which took just one week to complete.

Safety

Construction programme safely maintained during difficult weather conditions.

Quality

Detailed erection planning and scheduling combined with excellent on site engineering operations.

Speed

The project was completed in just 7 weeks on site.

Value

PCE installed some 147 arch units weighing up to 20 tonnes each to form the tunnel and a further 18 scalloped units which were placed at the entry and exit to the structure.

Let's Talk...

If you would like to discuss a project please contact our team to discuss your requirements...

What's New?

HybriDfMA Frame – PCE chosen for Brent Cross Town Plot...

View Article

PCE’s HybriDfMA Frame chosen for Silvertown Plot...

View Article

hyTower® for High-Rise Urban Living – PCE appointed Brent...

View Article
Let's Talk