Project Description

East Village N06, London

Speed

625m² residential floor plate constructed every 6 days and 4,750 no. Structural and 560 volumetric prefabricated modular M&E components installed in just 12 months.

Safety

Over 200,000 site man hours and up to 32 storeys delivered safely.

Value

Integrated façade and M&E systems delivered in conjunction with the construction of the superstructure reducing the overall programme by 30%.

Quality

Factory engineered ‘kit of parts’ coupled with extensive offsite preassembly delivered the highest levels of ‘as-built’ quality and predictability.

Location: East London, UK
Delivery team: Mace Group, PCE Ltd and Oranmore Precast Ltd
Client: Get Living
Architect: Hawkins Brown
Structural Engineer: Walsh


The benefits of HybriDfMA Living System construction:

Factory engineered ‘kit of parts’ coupled with extensive offsite preassembly delivered the highest levels of ‘as-built’ quality and predictability.


Integrated façade and M&E systems delivered in conjunction with the construction of the superstructure reducing the overall programme by 30%.