Topping Out at Block C – A Milestone for Fulton & Fifth

We are thrilled to announce the successful topping out of Block C at Regal’s Fulton & Fifth development - a key milestone in this exciting residential project, delivered through PCE’s hyTower® HybriDfMA build system.

Situated in the heart of Wembley, Fulton & Fifth comprises five high-rise blocks, delivering 876 modern apartments (around 40% affordable housing) alongside 33,000 sq. ft. of commercial space. Standing at 28 storeys, Block C is the tallest structure in the development, and one of the tallest structures in Brent.

With nearly 4,500 structural components assembled on-site for Block C, and over 17,000 pre-engineered elements across the project, hyTower® has been instrumental in driving certainty of outcome, safety, quality, speed, and value.

 

The Power of Offsite DfMA

By leveraging a precision-engineered ‘kit of parts’ approach, the hyTower® system has significantly streamlined construction and unlocked added value:

Coordinated, Efficient, and Fast – just-in-time delivery and standardised construction processes enable rapid on-site assembly, with up to 500 tonnes of hybrid components installed daily
Enhanced Quality – precision manufacturing ensures exact tolerances and assured quality
Reduced Risk – offsite means less site activity, requiring fewer site operatives, deliveries, and disruptions, enhancing safety and efficiency
Systemised DfMA – our systemised approach enhances productivity as well as certainty, despite reduced resource requirements
Integrated Solution – factory-fitted windows, façades, balconies, M&E, and utility services minimise site work
Sustainability Gains – achieving 239kgCO2e/m², in line with LETI’s 2020 targets, with embedded carbon reductions such as 75 tonnes saved by eliminating plasterboard in cores and stairs
Digital Certainty – real-time tracking, digital twin technology, and comprehensive quality management for a seamless, coordinated, and compliant build process

 

Daniel Frett, Project Lead for Regal, noted:

“Regal & PCE have achieved a huge milestone by topping out on Block C. Not only the tallest block in the London Borough of Brent but also in Regal’s history.  There have been several challenges on the way to the top but due to a collaborative working relationship, we have overcome the odds, achieving this significant feat, ahead of programme. Thanks go to the team at PCE for making this happen on site and working with their supply chain to enable the manufacture and delivery of all components to achieve an early completion.”

 

Through this highly efficient systemised ‘kit of parts’ approach, Fulton & Fifth exemplifies the future of high-rise residential construction; delivering high-quality homes faster, safer, and more sustainably.