Lower Broughton residential development, Salford, Manchester updates

The extent of PCE Ltd works on the scheme is the design, manufacture and construction of six single storey offsite engineered hybrid construction podium decks to support timber framed apartment blocks of up to 5 storeys and a further two single storey carpark decks, including access ramps for each deck.

  • The decks are being laid to a fall by PCE by varying the structural column levels
  • Each of the two single storey offsite engineered HybriDfMA car park decks are situated in between the apartment buildings
  • 760 structural precast concrete units required for the two carpark decks

Lower Broughton update 4 – third phase carpark decks

March 23rd, 2020|Comments Off on Lower Broughton update 4 – third phase carpark decks

Car parks are GO at Lower Broughton Following the successful delivery of Phase 1 and Phase 2 apartment podium decks for Countryside Properties in Salford, Manchester during 2019, PCE Ltd are soon to start constructing [...]

  • Residential podium decks completed by PCE in Lower Broughton
  • PCE's HybriDfMA system build approach in Salford
  • PCE's Offsite HybriDfMA solutions meet fast construction programme needs

Lower Broughton update 3 – residential podium decks completed

August 13th, 2019|Comments Off on Lower Broughton update 3 – residential podium decks completed

The offsite HybriDfMA solution benefits PCE Ltd has now completed construction of the six residential podium decks for Countryside Properties at Lower Broughton, Salford using their HybriDfMA system build approach. Over 900 offsite engineered precast concrete [...]

  • 910 structural precast concrete units have been manufactured offsite
  • PCE's Offsite Digital Engineering approach extensively incorporates 3D BIM modelling software

Lower Broughton update 2 – PCE’s Digital HybriDfMa approach

July 23rd, 2019|Comments Off on Lower Broughton update 2 – PCE’s Digital HybriDfMa approach

Featuring eight single storey podium decks PCE Ltd has utilised it's HybriDfMA system build approach for the eight single storey podium decks for Countryside Properties' Lower Broughton residential project. The Offsite Digital Engineering approach extensively incorporates [...]

  • Concept illustration of Lower Broughton residential development Salford in Manchester
  • The extent of PCE Ltd works on the scheme is the design, manufacture and construction

Lower Broughton residential development underway

July 18th, 2019|Comments Off on Lower Broughton residential development underway

Residential project in Salford, Manchester The Lower Broughton residential development scheme is part of a 15-year regeneration project with a partnership between Salford City Council and Countryside Properties. PCE Ltd has been working alongside Countryside [...]