Current projects

/Current projects
Current projects2018-11-19T10:23:31+00:00

Latest news about ongoing PCE projects

Vulcan Mill, Manchester

  • PCE Ltd has been appointed by Manchester based Russells Construction Ltd
  • The new building will sit adjacent to the original Vulcan Mill a former Victorian machine work
  • PCEs HybriDfma construction approach in Manchester
  • The offsite-engineered, HybriDfma structural solution from PCE
  • PCEs offsite-engineered, HybriDfma structural solution approach
  • Construction update at Vulcan Mill in Manchester
  • A composite concrete:steel support for the Hollowcore units
  • This part of the structure has been constructed using precast concrete columns
  • Steel reinforcement and insitu concrete was used with the Deltabeams by PCE

Vulcan Mill update 3 – construction of basement and under-croft parking complete

October 29th, 2018|Comments Off on Vulcan Mill update 3 – construction of basement and under-croft parking complete

Residential development project update PCE has successfully completed construction of the basement, under-croft parking and amenity areas for a 101-apartment residential development at Vulcan Mill in central Manchester for main contractor Russells Construction. This part [...]

Dakota Hotel Manchester

  • PCE complete offsite manufactured hybrid solution within the contract period
  • PCE delivered certainty for client GMI Construction in Manchester
  • The whole PCE team involved with the project have been outstanding from start to finish
  • PCE Ltd has now completed the construction of the offsite engineered Hybrid frame
  • Brick faced sandwich panel façade for the new Five Star Dakota Boutique Hotel
  • PCE used their HybriDfma approach
  • The construction team has completed the offsite engineered Hybrid frame

Dakota Hotel 12 – Hybrid frame construction complete

August 6th, 2018|Comments Off on Dakota Hotel 12 – Hybrid frame construction complete

Hotel superstructure design and build in Manchester PCE Ltd has completed the offsite manufactured Hybrid solution within the contract period, delivering certainty for client GMI Construction. PCE's offsite engineered Hybrid frame included a brick faced [...]

Kingston University Town House

Kingston University update 15 – time lapse video shows Town House construction

December 12th, 2018|Comments Off on Kingston University update 15 – time lapse video shows Town House construction

An offsite fabricated Hybrid construction approach PCE Ltd worked with main contractor Willmott Dixon during the tender phase to develop an offsite fabricated Hybrid solution for the concrete frame of the new Kingston University Town [...]

Durham University

  • Part of the PCE HybriDfMA approach
  • PCE has provided a key benefit for the client by the use of fully integrated architectural precast units
  • PCEs proven structural system HybriDfMA philosophies
  • PCEs units are manufactured in a controlled offsite factory environment

Durham University update 3 – the HybriDfMA design focus

December 19th, 2018|Comments Off on Durham University update 3 – the HybriDfMA design focus

An amalgamation of element interfaces with high repeatability The initial design processes for all of the structural components of the five new Durham University Mount Oswald four storey student accommodation blocks has been driven to achieve an [...]

Chapel Wharf, Manchester

  • The remaining two towers at Chapel Wharf are Blocks and D
  • Offsite pre-glazed external architectural envelope and balconies

Chapel Wharf update 15 – progress on blocks C and D and latest safety award

December 18th, 2018|Comments Off on Chapel Wharf update 15 – progress on blocks C and D and latest safety award

Offsite pre-glazed external architectural envelope PCE Ltd's work is proceeding at a good pace on blocks C and D of the nine hundred and ninety five unit Build to Rent apartment scheme being built by Sir [...]