Offsite construction

//Offsite construction

Chapel Wharf update 14 – first two towers structurally topped out

The precast concrete crosswall structural approach The first two apartment blocks have been structurally completed within the agreed construction programme as a result of PCE’s Offsite Engineered predominately precast concrete crosswall structural approach used on the nine hundred [...]

Chapel Wharf update 14 – first two towers structurally topped out 2018-10-17T12:41:19+00:00

Chapel Wharf update 13 – the top 5 offsite construction advantages

Crosswall construction with precast concrete Construction work by PCE Ltd is progressing at an impressive pace on the site of developer Dandara's nine hundred and ninety five build-to-rent apartment scheme at Chapel Wharf in Salford. PCE worked with [...]

Chapel Wharf update 13 – the top 5 offsite construction advantages 2018-08-30T10:28:20+00:00

Dakota Hotel 12 – Hybrid frame construction complete

Hotel superstructure design and build in Manchester PCE Ltd has completed the offsite manufactured Hybrid solution within the contract period, delivering certainty for client GMI Construction. PCE's offsite engineered Hybrid frame included a brick faced sandwich panel façade [...]

Dakota Hotel 12 – Hybrid frame construction complete 2018-08-06T15:37:35+00:00

Vulcan Mill project to begin shortly in Manchester

HybriDfma structural solution approach for residential development PCE Ltd has been appointed by Manchester based Russells Construction Ltd to provide the Design, Manufacture and Construction of an offsite engineered Hybrid Structure for The Loom, a residential development forming [...]

Vulcan Mill project to begin shortly in Manchester 2018-08-22T14:32:03+00:00

Kingston University update 11 – construction of the colonnade underway

Offsite fabricated hybrid solution for the concrete frame Kingston University appointed RIBA award winning Grafton Architects for their new landmark teaching building for their Penrhyn Road campus in Kingston Upon Thames. The six storey building will be the [...]

Kingston University update 11 – construction of the colonnade underway 2018-07-13T15:58:12+00:00

Chapel Wharf update 9 – how all this can be achieved with only 38 on site staff

The benefits of leaving behind the "traditional" construction approach A total of only thirty eight employees from PCE Ltd, comprising of highly skilled site operatives and technical and site management, are located on site currently at Chapel Wharf, Salford. [...]

Chapel Wharf update 9 – how all this can be achieved with only 38 on site staff 2018-07-13T16:35:11+00:00

Chapel Wharf update 8 – 2,900 offsite precast units in 34 weeks

How offsite manufacture keeps onsite construction moving The on site construction of Chapel Wharf, a residential project in Salford, Manchester for developer Dandara, is making considerable and rapid progress. PCE Ltd has been engaged as the specialist design and build [...]

Chapel Wharf update 8 – 2,900 offsite precast units in 34 weeks 2018-07-13T16:34:45+00:00

Dakota Hotel update 9 – level completed in only 2 weeks!

Level three of Manchester hotel complete PCE Ltd is currently installing the offsite engineered flooring units for level four of the forthcoming luxury five star Dakota Boutique Hotel project in Manchester. The structural elements of level three have now been completed, [...]

Dakota Hotel update 9 – level completed in only 2 weeks! 2018-07-13T11:28:36+00:00