Capella update 7 – solid core walls added at north end

1st to 2nd level structure well underway The Capella laboratory project is now progressing rapidly in Cambridge with offsite manufactured solid core walls being added to the north end of the site. PCE Ltd are working with project architects Fairhursts Design [...]

Capella update 7 – solid core walls added at north end 2018-07-13T15:18:03+00:00

Capella update 6 – hybrid construction project takes shape

Precast columns for multi-storey laboratory building Latest: 1st to 2nd level structure progressing The Capella building in Cambridge is being designed to provide world class scientific and research facilities with a stringent requirement to minimize vibrational effects when it is [...]

Capella update 6 – hybrid construction project takes shape 2018-07-13T15:16:13+00:00

Emirates Old Trafford update 7 – construction of 1st floor of hotel

Precast concrete units for Hilton Gardens Inn Update: last level one balcony slab being installed. The first floor walls are now arriving onsite and are being installed. PCE Ltd's hybrid offsite construction methods are once again being showcased - this [...]

Emirates Old Trafford update 7 – construction of 1st floor of hotel 2018-07-13T11:57:50+00:00

Capella update 3 – waterproof basement wall construction

Precast concrete walls arriving onsite The Capella, Cambridge project is progressing rapidly as precast components are arriving and being installed. Precast component production began earlier in the year, ensuring a rapid project delivery. PCE Ltd have an enviable [...]

Capella update 3 – waterproof basement wall construction 2018-07-13T15:13:40+00:00

Emirates Old Trafford update 2 – 3D modelling

PCE’s design team part of BIM system approach The Emirates Old Trafford Hotel project is a major step forward in the continuing growth of PCE Ltd. All structural engineering design and detailing for the project is being carried out [...]

Emirates Old Trafford update 2 – 3D modelling 2018-07-13T12:01:36+00:00

Kier choose PCE as superstructure construction partner

Hybrid construction for Capella Laboratory, Cambridge The building is being designed to provide world class scientific and research facilities with a stringent requirement to minimize vibrational effects when it is occupied and in use due to the very [...]

Kier choose PCE as superstructure construction partner 2018-07-13T15:10:15+00:00