Lower Broughton update 3 – residential podium decks completed

The offsite HybriDfMA solution benefits

PCE Ltd has now completed construction of the six residential podium decks for Countryside Properties at Lower Broughton, Salford using their HybriDfMA system build approach.

Over 900 offsite engineered precast concrete units were manufactured offsite and delivered to meet the overall onsite construction programme of thirteen weeks for the six podium structures.

 

Fast construction programme

Construction was carried out sequentially using a hundred ton telescopic crane with an average workforce on site during the construction period of only eight operatives. Once again PCE’s approach has demonstrated that their Offsite HybriDfMA solutions meet fast construction programme needs by reducing:
  • The number of onsite operatives
  • Health and Safety risks
  • The project's carbon footprint.

 