Kingston University update 12 - the first colonnade terrace unit and the HybriDfma advantage

Why the 16.3 tonne precast concrete unit was cast upside down

PCE Ltd has commenced erection of the terrace units that form part of the colonnade at the Kingston University Town House project, for which they are the specialist Design and Build Contractor and Willmott Dixon is the Main Contractor. The precast concrete unit shown being craned into place and installed (above) weighs 16.3 tonnes and has been cast incorporating recesses for drainage channels, falls and cross falls to the upper surface which has also been manufactured with a surface retarded finish. The precast concrete unit incorporates recesses for drainage channelsImage shows the top face of the finished cage with retarded soffit (left) and the slab's drainage gully. PCE’s precast coordinator, Paul Silker, had a major input into the production methodology for these units.
“We decided to cast the unit upside down thus enabling a high degree of accuracy to be achieved with the various falls required and control of the surface retardation. The large units on being demoulded were then turned with an electric belt turner.”
Large units on being demoulded were turned with an electric belt turnerTurning the offsite engineered 16.3 tonne precast concrete unit Nickie Brown, PCE’s Managing Director, remarked “Once again the PCE team has accomplished the provision of another high quality complex precast concrete unit type for this prestigious project: designed for manufacture and assembly, the HybriDfma approach enables the achievement of all architectural and engineering requirements”.

Further information

Kingston University update 11 – construction of the colonnade underway »

Kingston University update 10 – last of 315 precast frame beams installed on level 6 »

Kingston University update 9 – cantilever support structure » Kingston University update 8 – collaborative approach delivers Health, Safety and environmental benefits » Kingston University update 7 – concept becoming reality » Kingston University update 6 – level 2 vertical precast units and first steel atrium stairs installed » Kingston University update 5 – precast concrete elements in auditorium » Kingston University update 4 – Hybrid construction focus » Kingston University Town House update 3 – 229 Double Tee units » Kingston University Town House update 2 – first precast concrete elements erected » Kingston University Town House project underway » SaveSave
Let's Talk