Dakota Hotel update 6 – level 1 walls and Delta Beams installed

Bathroom pods lifted into hotel rooms in Manchester

PCE Ltd has now installed and grouted all the level one walls on the new Dakota Boutique Hotel project in Manchester.

Bathroom pods are being moved into position now that the level one Delta Beams have also been installed. Delta Beam units help to provide the structural hybrid frame solution, with insitu concrete being used where necessary to facilitate structural connections.

 

Precast concrete sandwich panels

Architectural brick faced precast concrete sandwich panels (shown in the images above) are being supplied for the hotel façade. They are currently being are supplied to site with windows fitted at the precast factory. This provides the considerable benefit of speeding up the final fit-out of the hotel, reducing the need for follow on trades, inner city deliveries and thus the carbon footprint.

Let's Talk