About the Project

1,032 car parking spaces – suspended floor area of 27,700m²

Tight site constraints including being in the city centre, one edge of the site abutting a river, and the footprint of the structure being close to all the site boundaries meant that PCE had to consider carefully the best choice of frame components to minimise deliveries and any potential road and site congestion.

The resultant design led to the extensive use of the PCE GT flooring system, with 877 GT units being used providing 21,757m² of the suspended floor area.

GT units are wet cast 400mm deep with the final floor finish being formed during casting as they require no insitu concrete structural topping, giving significant savings with regards total weight of concrete used, reduced site deliveries and programme savings.

For the Stafford MSCP this alone equates to a saving in concrete use of approximately 3,500 tonnes compared to other precast long span flooring options.

PCE Contiframe

PCE Contiframe concepts were used in the design of the structure including the casting of pairs of columns and the beam supported by them as single unit portals, with 133 of these being used. This has again significantly reduced the erection programme.

Improved site safety

Apart from enabling a faster erection programme the portal units manufactured to tight tolerances have improved the overall quality of the project with improved accuracy of fit. The reduction in lifting operations and on site work activity improves the overall safety on site.

PCE’s in house company systems enable full control of a project from design initiation through to on site handover. Using highly experienced and skilled construction teams together with the companies own cranes – for the Stafford project Liebherr LR 1160 and LR1130 crawler cranes as well Peri handrailing safety systems helps to ensure the certainty of safely delivering a first class project on time.

Further information

Precast Stafford car park now fully operational »

Precast hybrid car park construction »

The facts, figures and benefits of hybrid offsite construction »

Liebherr crawler cranes »

Peri handrailing safety systems »

Project Info

Scale

  • 14 split level MSCP with a suspended floor area of 27,700m²
  • Accommodating 1,032 car park spaces

Flexibility

  • 133 portal units comprising 2 columns and one beam, cast as one unit to reduce the erection period
  • PCE GT flooring units delivered to site with an anti skid finish cast into the top surface

Quality

  • Offsite manufacture in 5 carefully controlled QA facilities monitored by PCE.
  • This ensure that all units delivered were to approved standards of finish and dimensional tolerance.

Programme

  • Constructed on-site in 27 weeks with a maximum of 32 PCE site employees
  • 2 PCE owned Liebherr crawler cranes were deployed on site