Bracknell update 10 – last curved ramp beam is installed

Access ramp nearing completion at the Lexicon

The car park access ramp for the 1,300 space multi-storey car park at at the Lexicon Bracknell, which was entirely designed by and is being built by PCE Ltd, is rapidly being completed.

The ramp was constructed offsite utilising PCE’s own developed products and techniques.

The photographs (above) focus on the installation of the final curved ramp beam to arrive onsite.

Like the recently completed multi storey car park constructed by PCE for Stafford Town Centre, the structure is not just simply a car park: the retail space at the front is also part of the PCE design and build package.

Car park construction

PCE is able to offer complete multi-storey structural frame solutions for car park projects using the latest technology in design and offsite manufacture.

High quality external and internal architectural finishes can be incorporated into the project and the structure safely erected with minimal perimeter scaffolding requirements.

Bracknell update 9 – precast “making a complex structure easy” »

Bracknell update 8 – the advantages of offsite precast construction »

Bracknell update 7 – preparation for the car park ramp »

Bracknell update 6 – first ramp column goes in »

Bracknell update 5 – how offsite approach reduces town centre congestion »

Bracknell update 4 – PCE’s cranes help rapid progress »

Bracknell update 3 – car park and retail outlet build gathers momentum »

Bracknell update 2 – team safety award for PCE »

Bracknell update 1 – GT long span floor units »

Tags: