The Birmingham East Side Locks high rise student accommodation project is progressing at an impressive pace by utilising the offsite engineering solutions that have been constructed by PCE Ltd.

 

PCE, by working with 3 erection crews and crawler cranes, have been erecting 300 tonnes of precast concrete units per day - including architectural finished units - for this prestigious development. On-site construction is carried out by PCE to the highest quality that can be achieved, together with savings in programme periods and enhanced environmental benefits. Health and Safety considerations are always of paramount importance.